Line 2 will connect Chapinero with Suba along a 15.5 km route with 11 stations, interchanging with Line 1 at Calle 72. The project is currently in international public re-tender.

Project status

Current phase: International public re-tender

The first tender round was declared void in April 2026. Contract award is expected in Q1 2027, with construction targeted to begin around 2030.

Source EMB / prensa (Wikipedia L2MB, Semana, Infobae) (as of July 2026)

Line 2 by the numbers

Length
15.5 km
Stations
11
Localities
Chapinero, Barrios Unidos, Engativá, Suba
End-to-end ride
~20 min

The 11 planned stations

Names are Empresa Metro de Bogotá (EMB) working labels — none is final yet.

  1. 1. Calle 72Line 1 interchange

    Calle 72 - Av. Caracas

  2. 2. NQS

    Calle 72 - Av. NQS

  3. 3. Carrera 68

    Calle 72 - Av. Carrera 68

  4. 4. Avenida Boyacá

    Calle 72 - Av. Boyacá

  5. 5. Cali

    Calle 72 - Carrera 80

  6. 6. Calle 80

    Av. Ciudad de Cali - Calle 80

  7. 7. Carrera 91

    Av. Ciudad de Cali - Carrera 91

  8. 8. Humedal

    Calle 127 - Carrera 93 (humedal Juan Amarillo)

  9. 9. ALO Sur

    Av. Longitudinal de Occidente - Calle 129D

  10. 10. ALO Norte

    Av. Longitudinal de Occidente - Calle 139

  11. 11. Fontanar

    Av. Calle 145 - Carrera 141B (Fontanar del Río)